DUS6.1 regulary test of power backup system // DUS6.1 Turnusmäßiger Generator-Lasttest
Scheduled Maintenance Report for plusserver
Completed
The scheduled maintenance has been completed.
Posted Sep 29, 2021 - 14:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 29, 2021 - 13:02 CEST
Scheduled
We would like to inform you about the upcoming regular test of the Datahub DUS6.1 power backup system by PlusServer technicians.

This will take place on :

Wednesday, 29.09.2021 between 13:00 am and 14:00 pm (CET)

A test run will take place for 30 minutes within the specified time. This test is performed under load of the connected infrastructure.

An impairment of the power supply is not to be expected, but cannot be completely excluded.

If you have any further questions, please do not hesitate to contact us via the channels known to you with reference DCO-2062 .

--

Hiermit möchten wir Sie über den bevorstehenden turnusmäßigen Test der Netzersatzanlage am Datahub DUS6.1 durch PlusServer-Techniker informieren.

Dieser findet statt am :

Mittwoch, den 29.09.2021 zwischen 13:00 Uhr bis 14:00 Uhr (MESZ)

In der angegebenen Zeit wird für 30 Minuten ein Testlauf stattfinden. Dieser Test erfolgt unter Last der angeschlossenen Infrastruktur.

Eine Beeinträchtigung der Energieversorgung ist nicht zu erwarten, kann aber nicht vollständig ausgeschlossen werden.

Haben Sie weitere Fragen hierzu, so stehen wir Ihnen über die Ihnen bekannten Kanäle gerne zur Verfügung mit Verweis auf DCO-2062 .
Posted Sep 23, 2021 - 17:33 CEST
This scheduled maintenance affected: Sites (DUS6.1 DataHub [DE-WEST-2]) and Services (Power).