Generator load test - Generator Lasttest UPS-6 (MUC2)
Scheduled Maintenance Report for plusserver
Completed
The scheduled maintenance has been completed.
Posted Feb 22, 2024 - 11:00 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 22, 2024 - 08:00 CET
Scheduled
Dear Customer,

Please note the following maintenance announcement from Equinix.

--

Sehr geehrter Kunde,

bitte beachten Sie nachfolgende Wartungsankündigung von Equinix.

DATUM: 22-FEB-2024 - 22-FEB-2024

ZEITRAUM: 22-FEB-2024 - 22-FEB-2024

LOKAL: DONNERSTAG, 22 FEB 08:00 - DONNERSTAG, 22 FEB 11:00
UTC: DONNERSTAG, 22 FEB 07:00 - DONNERSTAG, 22 FEB 10:00

IBX: MUC2

AUSWIRKUNG AUF DEN SERVICE:

• Strom
• Die Lasten werden auf den Generator übertragen
• Die USV-Lasten bleiben auf ihrer primären USV-geschützten Quelle
• Die Systemredundanz wird aufrechterhalten
• Kühlung
• Die Systemredundanz wird aufrechterhalten

BESCHREIBUNG: Bitte beachten Sie, dass Equinix den quartalsmäßigen Generator-Lasttest im Datacenter IBX MUC2 an der UPS-5 an der genannten Zeit durchführen wird.

Dies ist ein regelmässiger Test der Generatoren, der in einer kontrollierten Art und Weise durchgeführt wird.

Während des Tests wird UPS5 auf eine Lastbank umgeschaltet. In dieser Zeit steht UPS5 für andere UPS-Systeme als Reserve-Anlage nicht zur Verfügung.

Die Equinix Techniker werden vor Ort eng mit den Servicetechnikern der Systemlieferanten zusammenarbeiten um sicher zu stellen, dass diese Wartung reibungslos ablaufen wird.

Diese Aktivität ist genau beschrieben und geplant, um für ihr Unternehmen nachvollziehbar zu sein.

Während dieser Zeit werden alle Dienstleistungen wie Smart Hands, Installationen, Besuche usw. normal gemäß unseren Prozeduren weitergeführt.

Während dieses Zeitraums werden alle Dienstleistungen (Smart Hands, Installationen, Arbeitsbesuche usw.) gemäß unseren normalen Verfahren fortgesetzt.

Sollten Sie Fragen zu dieser Aktivität haben, steht Ihnen der Global Service Desk für aktuelle Statusinformationen oder zusätzliche Details zur Verfügung. Bitte verweisen Sie auf CHG0032893.
*****************************************************************************

Dear Equinix Customers,

DATE: 22-FEB-2024 - 22-FEB-2024

SPAN: 22-FEB-2024 - 22-FEB-2024

LOCAL: THURSDAY, 22 FEB 08:00 - THURSDAY, 22 FEB 11:00
UTC: THURSDAY, 22 FEB 07:00 - THURSDAY, 22 FEB 10:00

IBX: MUC2

SERVICE IMPACT:

• Power
• Loads will be transferred to generator power
• UPS loads will remain on their primary UPS protected source
• System redundancy will be maintained
• Cooling
• System redundancy will be maintained

DESCRIPTION: Please be advised, that Equinix will perform the quarterly Generator Load Test in Data Centre IBX MUC2 at UPS-5 on the above mentioned time.

During the test, UPS-5 is switched to a load bank. During this time, UPS5 is not available for other UPS systems as a backup system.

Equinix engineers will work closely on-site with equipment system vendors and service providers to ensure that the maintenance is non-intrusive.

This activity is fully scripted and designed to be transparent to your operations.
During this period, all services (Smart Hands, installations, work visits, etc.) will continue in accordance with our normal procedures.

The equipment being maintained supports your circuits indicated in the table:

Impacted Assets

Account #Cage #Cabinet #Serial #Circuit Type
100295M4S40201024413416Redundant
100295M4S40202147155534Redundant
100295M4S40202034413424Redundant
100295M4S40201144413390Redundant
100295M4S40202044413426Redundant
100295M4S40202147155531Primary
100295M4S40202137155532Primary
100295M4S40201034413323Primary
100295M4S40201084413330Primary
100295M4S40202014413352Primary
100295M4S40201054413327Primary
100295M4S40201104413347Primary
100295M4S40201144413351Primary
100295M4S40202094413372Primary
100295M4S40202114413380Primary
100295M4S40201054413402Redundant
100295M4S40202094413419Redundant
100295M4S4020101239001.102Redundant
100295M4S40201034413412Redundant
100295M4S40202074413421Redundant
100295M4S40202014413388Redundant
100295M4S40201124413394Redundant
100295M4S40201094413398Redundant
100295M4S40201074413400Redundant
100295M4S40202114413417Redundant
100295M4S40202034413365Primary
100295M4S40201014413321Primary
100295M4S40201134413350Primary
100295M4S40202054413368Primary
100295M4S40201124413349Primary
100295M4S40202074413370Primary
100295M4S40202024413386Redundant
100295M4S40201104413397Redundant
100295M4S40202127155530Primary
100295M4S40202137155535Redundant
100295M4S4020101239001.101Primary
100295M4S40202054413423Redundant
100295M4S40202127155533Redundant
100295M4S402010713285871Redundant
100295M4S40201044413325Primary
100295M4S40201094413343Primary
100295M4S40202024413362Primary
100295M4S40202084413371Primary
100295M4S40201064413328Primary
100295M4S40201114413348Primary
100295M4S40202104413377Primary
100295M4S40201014413385Redundant
100295M4S40201134413393Redundant
100295M4S40201084413399Redundant
100295M4S402010713285870Primary
100295M4S40201114413395Redundant
100295M4S40201064413401Redundant
100295M4S40202104413418Redundant
100295M4S402-4413274_MPH-
100295M4S40201044413406Redundant
100295M4S40202084413420Redundant
100295M4S40202064413422Redundant
100295M4S402-4413427_MPH-
100295M4S40201024413322Primary
100295M4S40202064413369Primary
100295M4S40201074413329Primary
100295M4S40202044413366Primary

During this period, all services (Smart Hands, installations, work visits, etc.) will continue in accordance with our normal procedures.

The Global Service Desk is available to provide up-to-date status information or additional details, should you have any questions regarding the maintenance. Please reference CHG0032893.
Posted Jan 16, 2024 - 09:06 CET
This scheduled maintenance affected: Services (Power).