DUS4 Scheduled Generator Load Transfer Test Feed 1
Scheduled Maintenance Report for plusserver
Completed
The scheduled maintenance has been completed.
Posted Aug 03, 2021 - 18:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 03, 2021 - 08:00 CEST
Scheduled
Herewith we like to inform you about the scheduled generator load transfer test performed by Equinix. The maintenance are going to be carried at

LOCAL: TUESDAY, 03 AUG 08:00 - TUESDAY, 03 AUG 18:00
UTC: TUESDAY, 03 AUG 06:00 - TUESDAY, 03 AUG 16:00

The Power feeds to all cabinets will remain protected by Equinix Uninterruptible Power Systems (UPS) at all times.

We do not expect your booked services to be impaired.
Nevertheless, as with all maintenance work, we would like to point out that in the unexpected event of complications, unavailability may occur.

If you have further questions about this process, we are at your disposal through the channels known to you with reference PSCS-53072

--

Hiermit möchten wir Sie über den bevorstehende Lastübertragungstest an den Generatoren durch den Rechenzentrum-Betreiber Equinix informieren. Die Wartungsarbeiten finden statt am:

LOKAL: DIENSTAG, 03 AUG 08:00 - DIENSTAG, 03 AUG 18:00
UTC: DIENSTAG, 03 AUG 06:00 - DIENSTAG, 03 AUG 16:00

Die Stromversorgungen zu den Racks bleiben jederzeit durch die unterbrechungsfreien Stromversorgungssysteme (USV) der Equinix geschützt.

Wir erwarten bei diesen Wartungsarbeiten keine Auswirkungen auf Ihre gebuchten Produkte. Trotzdem möchten wir wie bei allen Wartungsarbeiten darauf hinweisen, dass im unerwarteten Fall von Komplikationen eine Nichterreichbarkeit entstehen kann.

Haben Sie weitere Fragen hierzu, so stehen wir Ihnen über die Ihnen bekannten Kanäle gerne zur Verfügung unter der Referenz PSCS-53072.
Posted Jul 06, 2021 - 19:08 CEST
This scheduled maintenance affected: Sites (DUS4) and Services (Power).