DUS6.1 General overhaul cooling pumps
Scheduled Maintenance Report for plusserver
Completed
The work was carried out successfully.
Posted Feb 03, 2021 - 16:41 CET
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Feb 02, 2021 - 08:00 CET
Scheduled
We would like to inform you that we will carry out necessary general overhaul on the cooling water pumps in DUS6.1. These will take place on:

02.-04. February 2021, each between 08:00 and 18:00 o'clock (CET)

The work is necessary to ensure maintenance and safety in our climatic supply. We try to complete them as quickly as possible and with as little impact on your systems as possible.

Due to the existing redundancy, we do not expect any impairment of your booked services.
Nevertheless, as with all maintenance work, we would like to point out that in the unexpected event of complications, unavailability may occur.

If you have any further questions regarding this procedure, we will be at your disposal through the channels you are familiar with. reference ticket: #7426753
Posted Jan 25, 2021 - 14:43 CET
This scheduled maintenance affected: Sites (DUS6.2 DataHub [DE-WEST-2]).