DUS6.2 monthly generator load test // DUS6.2 monatlicher Generator-Lasttest
Scheduled Maintenance Report for plusserver
Completed
The scheduled maintenance has been completed.
Posted May 10, 2022 - 13:00 CEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 10, 2022 - 12:01 CEST
Scheduled
We would like to inform you about the upcoming regular test of the Datahub DUS6.2 power backup system by PlusServer technicians.

This will take place on :

Tuesday, 10 May 2022 between 12:00 am and 13:00 pm (CET)

A test run will take place for 30 minutes within the specified time. This test is performed under load of the connected infrastructure.

An impairment of the power supply is not to be expected, but cannot be completely excluded.
If you have any further questions, please do not hesitate to contact us via the channels known to you with reference to DCO-8246

--

Hiermit möchten wir Sie über den bevorstehenden turnusmäßigen Test der Netzersatzanlage am Datahub DUS6.2 durch PlusServer-Techniker informieren.

Dieser findet statt am :

Dienstag, den 10.05.2022 zwischen 12:00 Uhr bis 13:00 Uhr (MESZ)

In der angegebenen Zeit wird für 30 Minuten ein Testlauf stattfinden. Dieser Test erfolgt unter Last der angeschlossenen Infrastruktur.

Eine Beeinträchtigung der Energieversorgung ist nicht zu erwarten, kann aber nicht vollständig ausgeschlossen werden.

Haben Sie weitere Fragen hierzu, so stehen wir Ihnen über die Ihnen bekannten Kanäle gerne zur Verfügung mit Verweis auf DCO-8246
Posted May 04, 2022 - 14:52 CEST
This scheduled maintenance affected: Sites (DUS6.2 DataHub [DE-WEST-2]) and Services (Power).